DEPUTY GENERAL DIRECTOR LE QUOC TUAN VISITS AND WORKS AT LONG THANH INTERNATIONAL AIRPORT PROJECT

09/10/2025 22:06

On October 8, 2025, Deputy General Director Le Quoc Tuan conducted a working visit to inspect the construction progress at the Long Thanh International Airport Project.

Deputy General Director Le Quoc Tuan inspected the construction items being executed by Phuc Hung Holdings at the Long Thanh International Airport Project

Deputy General Director Le Quoc Tuan inspected the construction items being executed by Phuc Hung Holdings at the Long Thanh International Airport Project

The Deputy General Director praised the Project Management Board for their serious and professional working spirit, particularly in construction quality control, orderly and clean site arrangement, and scientific management of materials and equipment. He also instructed the management team to continue upholding their sense of responsibility, maintain discipline, and ensure the completion of glass installation for the passenger boarding bridges by early December. He emphasized the need to further strengthen quality control to secure construction progress and quality – key factors that reinforce the reputation of Phuc Hung Holdings. The Deputy General Director stressed that the entire project team must remain highly focused, proactively review design details, and ensure sufficient material supply to maintain a continuous, safe, and well-planned construction process.

Deputy General Director Le Quoc Tuan presided over a working meeting at the Project Management Board of the Long Thanh International Airport Project

Deputy General Director Le Quoc Tuan presided over a working meeting at the Project Management Board of the Long Thanh International Airport Project

Construction of the passenger terminal at Long Thanh International Airport is well underway toward completion

Construction of the passenger terminal at Long Thanh International Airport is well underway toward completion

Overall view of construction at the Passenger Terminal of the Long Thanh International Airport Project

Currently, at Package No. 5.10 – Construction and Installation of the Passenger Terminal Building, implemented by Phuc Hung Holdings and other members of the Vietur Consortium, the construction volume has reached approximately 75%. The entire structural work has been completed, and masonry works are fundamentally finished. Installation of the main steel truss system has reached 100% completion, while the glass façade installation has reached around 45%.

In the construction area undertaken by Phuc Hung Holdings, the erection of the main steel structure for the roofing system has been completed, and roofing layer installation has reached 70% progress, which is expected to be completed by the end of October. Meanwhile, glass façade installation has reached 80% of the workload. Finishing works such as tile and stone installation, doors, interior ceiling systems, and roof ceilings are being carried out simultaneously, ensuring the overall progress of the package.

 