As of now, the installation of bored piles is approximately 45% complete, and driven pile work stands at about 25% of the total volume. Regarding the technical infrastructure, significant progress has been made on lines D7, N1, and N2, reaching roughly 30% completion. Furthermore, two tower cranes (TC01 and TC03) have been successfully erected and are operating stably, positioning the site to smoothly transition into the vertical construction phase.
The Taseco Thai Nguyen site is currently maximizing the mobilization of manpower and equipment as it enters the critical basement construction phase. Construction crews are actively carrying out basement excavation along axes 36–41 and 1–8, while simultaneously undertaking the sequential installation of blinding concrete, formwork, and reinforcement for the underground structure. This marks a pivotal advancement, signaling a new, accelerated development stage for the Project.
Driven by strong determination and a high sense of responsibility, the Site Management Board and all staff and employees of Phuc Hung Holdings on site are making daily efforts to accelerate construction progress, ensuring the Project’s safety, schedule, and quality meet the Investor's requirements.
Some photos from the Site: