Duong river surface water plant
Main contractor
Construction of main items of water plant with a capacity of 300,000 m3/day.
214 days
Gia Lam, Hanoi
* Level I project:
* Project scale:
- Construction of treatment area: Including 05 main items: Flow separation area, mixing concrete, pretreatment, sedimentation, filter tank, chemical and chlorine house, storage tank , Clean water pumping station;
- Sludge treatment area: Including 06 main items: Wash water recovery tank; Conditioned calves; Sludge compression tank; House for sludge dewatering machine; Mud drying yard; Factory area.
* Scope of work: Construction of main items.
* Construction start: 2017.