With a high sense of responsibility, strong determination, and close coordination among all participating entities, the Site Management Board has successfully completed the concrete pouring for 03 out of 06 zones of the B2 basement floor. The entire B2 basement floor is scheduled for completion within June in strict accordance with the set plan. Moving forward, construction will proceed with the B1 floor beams, slabs and the 0.000 level, aiming to finalize the structure of the building's 2 basements and establish a solid foundation for the upcoming superstructure construction phase.
Below are some construction images from the site: