INVESTMENT IN THE CONSTRUCTION OF LIME PRODUCTION LINE 2 WITH A CAPACITY OF 100,000 TONS/YEAR - BA RIA VUNG TAU

Name of project
Name of project:

Investment in the construction of lime production line 2 with a capacity of 100,000 tons/year - Ba Ria Vung Tau

Contract type
Contract type:

Construction package
Construction package:

Implementation progress
Implementation progress:

2013 - 2014

Project location
Project location:

Thành phố Vũng Tàu, Ba Ria - Vung Tau

INVESTMENT IN THE CONSTRUCTION OF LIME PRODUCTION LINE 2 WITH A CAPACITY OF 100,000 TONS/YEAR - BA RIA VUNG TAU
PROJECT OVERVIEW

PROJECT OVERVIEW

* Project scale: Kiln, lime and coal storage silo, coal mill house, kiln head house, heat exchanger tower, machine foundation, coal warehouse, lime warehouse

 


* Construction start date: 2013

PHOTOS OF THE PROJECT