Thuy Tien Ecopark mid-rise area TRT05- TRT06
General contractor for design & construction
Project design and construction contract
459 days
Van Giang, Hung Yen
* Project scale:
* 02 mid-rise buildings:
TRT05:
- 01 basement
- 01 podium floor
- 08 tower block floors, total area: 3,162m2
TRT06:
- 01 basement, area: 2,897m2
- 01 floor podium, total area: 1,243m2
- 08 floors of tower block, total area: 3,571m2
* Scope of work: General contractor for design, structural construction, finishing, mechanical and electrical work
* Commencement: February 23/ 2022