Florence Tower Complex Project

Name of project
Name of project:

Florence My Dinh Apartment - Hanoi

Contract type
Contract type:

General contractor for design & construction

Construction package
Construction package:

Construction, supply, installation, acceptance, completion, warranty of all structural work, mechanical and electrical completion

Implementation progress
Implementation progress:

720 days

Project location
Project location:

Nam Tu Liem, Hanoi

Florence Tower Complex Project
PROJECT OVERVIEW

PROJECT OVERVIEW

- Project level: Level I
- Project scale: 
+ 03 basements, area;
+ 02 25-storey towers, total area.
- Scope of work: 
+ Construction of the underground part of the building;
+ Construction, equipment installation and building completion;
+ Construction, supply, installation, acceptance, completion, and warranty of all structural, finishing, electromechanical and refrigeration work.
- Construction start time: October 2017
 