P7
General contractor
12/2019
Dai Mo, Nam Tu Liem, Hanoi
- Project level: Level I
- Project scale:
+ Construction and finishing of basements P5, P6, P7; construction and finishing of Tower P7 with 39 floors
+ Total construction floor area: 49,775 m²
- Construction schedule:
+ Foundation and basement: 180 days
+ Superstructure and finishing: 345 days
- Construction start time:
+ Foundation and basement: 12/2019
+ Superstructure: 2021
- Construction package:
+ Construction and finishing of basements P5, P6, P7
+ Finishing of the superstructure of Tower P7
+ Construction of the superstructure and rough finishing of Tower P7
- Construction start time:
+ Foundation and basement: 12/2019
+ Superstructure: 2021