Main Contractor
Construction of one raw material silo and one substandard clinker silo under Package No.10 of the But Son Cement Plant – Production Line 2 Project
2007 – 2008
Thanh Sơn, Kim Bảng, Ha Nam
- Package scale:
+ 01 raw meal silo and 01 substandard clinker silo;
+ 01 substandard clinker silo: D = 11m, H = 32.5m; 01 raw meal silo: D = 15.8m, H = 55m, floor thickness = 0.8m;
+ Capacity: 4,000 tons of clinker per day, equivalent to 1.6 million tons of cement per year;
- Construction package: Construction of one raw meal silo and one substandard clinker silo under Package No. 10
- Construction start time: July 2007.