- Construction of piles, foundations, silo slip walls, silo base slab, and finishing wor
2003 - 2004
Quang Sơn, Tam Điệp, Ninh Binh
- Construction package: +Cement grinding, bagging, and dispatching silos
+ Limestone and clay crushing station, conveyors transporting limestone and clay to storage
+ Construction of piles, foundations, silo slip walls, silo base slab, and finishing works
+ 01 homogenizing silo for raw materials: Diameter 20.8 m, Height 78 m, including roof beam lifting during slip
+ 02 clinker silos: Diameter 25 m, Height 52 m; prestressed cable for silo shell
+ 01 by-product silo: Diameter 10 m, Height 20 m
- Construction start time: 2003