Construction Contractor
Construction of Package XD3 under Production Line No. 2 of Chinfon Cement Plant
2007 – 2008
Thủy Nguyên, Hai Phong
* Project level: Level I
* Project scale:
04 cement silos: Diameter 18 m; Height 57.8 m
Production capacity: 4,000 tons clinker/day, equivalent to 1.6 million tons of cement/year
* Construction start time: 2007