AP Consortium Contractor
Construction, Supply, and Installation of Building Equipment
450 days
Tan Binh, Ho Chi Minh
Package No. 9 includes the following main components:
- Main Air Traffic Control Center Building: Construction area of 2,360 m²
- Technical Station Building: Including power supply systems, domestic water, and fire protection pumping systems, with a construction area of 290 m²
- Antenna Towers: Two towers, each 65 meters high, with a construction area of 242 m²
- Internal Roads and Yards: Construction area of 2,800 m²
- Construction start time: July 28, 2023
- Handover Date: May 19, 2025